PA DEP halts new pipeline permits for Mariner East, cites ongoing violations with Revolution pipeline | StateImpact Pennsylvania Skip Navigation

PA DEP halts new pipeline permits for Mariner East, cites ongoing violations with Revolution pipeline

Wolf administration: PUC should take more 'aggressive' action against pipeline builder

  • Susan Phillips
The site of the Revolution Pipeline explosion that occurred in September 2018. Officials have said said heavy rain caused a landslide, leading to the explosion, which destroyed a house.

Marcellus Air

The site of the Revolution Pipeline explosion that occurred in September 2018. Officials have said said heavy rain caused a landslide, leading to the explosion, which destroyed a house.

Jon Hurdle / StateImpact Pennsylvania

Crews worked on Monday Jan. 21 to stabilize a new sinkhole that opened up at Lisa Drive, a suburban development in West Whiteland Township, Chester County where Sunoco operates its Mariner East pipelines.

The Pennsylvania Department of Environmental Protection says Energy Transfer hasn’t complied with an order related to the recent explosion of the Revolution pipeline outside Pittsburgh, so it has halted reviews of new water crossing permits the company wants for its natural gas liquids lines Mariner East 2 and 2x.  

Energy Transfer is the parent company of Sunoco Pipeline, which built the Revolution line and the 350-mile long Mariner East pipelines. The Revolution pipeline will also remain out of service until the company meets DEP’s conditions, the agency said Friday.

In September, heavy rains caused a landslide, resulting in an explosion that destroyed a house in Center Township, Beaver County. DEP’s investigation found the company had violated permit obligations, which included unreported landslides and erosion into nearby streams. DEP executive deputy secretary Ramez Ziadeh wrote to Sunoco that it had failed to comply with the agency’s order issued in October.

DEP says further investigations by DEP inspectors, most recently in January, uncovered continued violations of Energy Transfer’s erosion and sedimentation permits, a violation of the state’s Clean Streams Law.

“In October, DEP cited ETC for sediment-laden discharges into waterways, improperly maintained erosion controls, and failure to stabilize disturbed areas,” DEP Secretary Patrick McDonnell said. “Disappointingly, many of these issues persist.”

Gov. Tom Wolf called for the Legislature to enact pipeline reforms, and asked the Public Utility Commission to step up its oversight of Energy Transfer/Sunoco’s Mariner East pipeline project.

“There has been a failure by Energy Transfer and its subsidiaries to respect our laws and our communities,” Wolf said in a statement. “This is not how we strive to do business in Pennsylvania, and it will not be tolerated.”

The company has 27 Mariner East 2 permits under review, most of which are related to pending construction in Chester County, where pipeline work caused dangerous sinkholes that exposed the natural gas liquids line Mariner East 1. That line is not operating pending review by the Public Utility Commission. Mariner East 2 continues to ship product using a 12-inch work-around-line, and this order does not halt its operation.

Lisa Dillinger, a spokeswoman for Energy Transfer, said the company has told the DEP and the governor’s office that it’s committed to complying with all of its permits and state regulations.

“This action does not affect the operation of any of our in-service pipelines or any areas of construction where permits have already been issued,” Dillinger said in an email. “We look forward to continuing to work with the DEP throughout this process.”

The Mariner East project has been plagued by mishaps and delays caused by drilling mud spills and sinkholes. The DEP has halted construction at times, issued more than 80 violations, and penalized the company $12.6 million for permit violations. The explosion in September on the Revolution pipeline created more fear among residents who live close to the company’s Mariner East lines, especially in Chester County where sinkholes have exposed Mariner East 1.

Scott Blanchard / StateImpact Pennsylvania

The map shows the Mariner East 2 pipeline’s path across 17 Pennsylvania counties on its way to the Marcus Hook industrial complex in Delaware County, where the natural gas liquids it carries will be shipped overseas to make plastics. The map was built using state Department of Environmental Protection shapefiles of the route for which DEP issued permits. The line extends west into Ohio.

Residents of Chester County have been especially vocal in urging Wolf to take action. Chester County District Attorney Tom Hogan has opened a criminal investigation into the company’s practices.

Wolf has directed the Pennsylvania Emergency Management Agency to step in and assist local governments with emergency plans. The governor’s deputy chief of staff Sam Robinson says the PUC needs to take more “aggressive” action toward the company.

The PUC said it is reviewing Wolf’s comments before responding.

“We’ve heard from local law enforcement folks, from local emergency responders, from local school districts that the communications have been abysmal from Energy Transfer,” Robinson said. “And we’re calling on the PUC to aggressively push Energy Transfer to comply with all of the emergency requirements, make sure all federal requirements are being kept so that these communities can understand the potential risks of the pipeline and deal with them in the unlikely event of an actual emergency.”

Energy Transfer’s spokeswoman Lisa Dillinger defended the company’s record on communication. She says the company hosted more than 700 township meetings, conducted sessions with 2,342 emergency responders and held emergency preparedness meetings with 36 schools in 17 counties.

Gov. Wolf  urged lawmakers to pass a set of rules that would grant siting authority to the PUC, require companies to provide emergency information to schools within 1,000 feet of a pipeline, force pipeline operators to meet with emergency managers to develop evacuation plans, and mandate installation of automatic shut-off valves in highly population areas.

The pipeline safety group Del-Chesco United released a statement calling the DEP’s action Friday “a good start,” but said Wolf should go further.

“Sunoco’s cobbled-together workaround pipeline is still transporting industrial quantities of dangerous materials next to our homes, schools, and businesses,” read the statement. “Every day that the Governor allows any part of Mariner East to stay in operation without the credible emergency plan required by existing regulations is a day our communities are left just hoping for the best.”

Up Next

Lawmakers’ Clairton Coke Works hearing draws suggestions, criticism over fire response