Shale Play

Natural Gas Drilling in Pennsylvania

Well: Marquardt 8494H

Operated by

Xto Energy Inc

Violations

7

Since Jan. 1, 2009

  • No violations
  • One or more violations

Violation Details

Xto Energy Inc has been fined $227,199 for violations in Pennsylvania (since Jan. 2009)

Inspection Date Code Type Resolved
10/6/2010 Failure to install, in a permanent manner, the permit number on a completed well Administrative 11/16/2010
1/19/2010 Failure to maintain 2' freeboard in an impoundment Administrative 3/1/2010
12/21/2009 Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) Environmental Health and Safety 1/19/2010
12/21/2009 Improper encapsulation of waste Administrative 1/19/2010
10/27/2009 Failure to maintain 2' freeboard in an impoundment Administrative 10/27/2009
10/7/2009 Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) Environmental Health and Safety 10/6/2010
10/7/2009 E&S Plan not adequate Administrative 10/6/2010